FERC rejects bigger Amazon data-centre load at Talen’s Susquehanna nuclear plant
See how this story connectsFERC voted 2-1 on 1 November 2024 (docket ER24-2172) to reject PJM’s amended interconnection agreement that would have raised the data-centre load co-located at Talen’s Susquehanna nuclear plant from 300MW to 480MW. Talen had sold its 960MW Cumulus data-centre campus to Amazon Web Services in March; Exelon and AEP had protested the filing.
Why it matters
Data-centre developers seeking power directly from existing plants learned that grid regulators would scrutinise co-location deals that bypass the shared grid.
- When
- 1 Nov 2024
- ID
WTA-N-2024-0137- Where
- United States
- Who
- FERC, PJM, Talen Energy, Amazon Web Services; Mark Christie, Willie Phillips
- Topics
- Energy and power, Data centres
Summary by wheresthe.ai, from Troutman Pepper Energy Report and the reporting credited above. We could not open the primary document, so it is marked Reported. Checked against the source on 9 Oct 2026.
Source copy: download the page as saved on 18 Oct 2026 (PDF). Also held by the Internet Archive.
Data to measure this
Compare the years before 2024 with the years since in these series.
- Epoch AI: frontier AI data centresEpoch AISite-level timelines of IT power, compute (H100-equivalents) and capital cost for large AI data centres.
- IEA Energy and AI dataInternational Energy AgencyWorld and regional data-centre capacity, power usage effectiveness, load factor and electricity use.
- Epoch AI: GPU clusters (archived)Epoch AIMore than 500 GPU clusters and AI supercomputers with country, owner, performance, power and cost.
Cite this story
WTA-N-2024-0137: “FERC rejects bigger Amazon data-centre load at Talen’s Susquehanna nuclear plant.” wheresthe.ai, 1 Nov 2024. https://wheresthe.ai/d/us-ferc-rejects-talen-amazon-susquehanna-isa-2024-11/ (source: Troutman Pepper Energy Report).
Spotted an error? Email [email protected].