FERC orders six US grid operators to fix or defend rules for connecting data centres

See how this story connects

After the Energy Secretary used a rarely invoked power in October 2025 to ask FERC to consider rules for connecting loads above 20MW, FERC chose six tailored Section 206 show-cause orders to PJM, MISO, SPP, CAISO, ISO-NE and NYISO instead of one national rule, defining a large load as 50MW or more. Each must justify its tariff or propose reforms covering study procedures, network-upgrade cost recovery, co-location, flexible-load service and generation adequacy, with responses due 17 Aug 2026.

Why it matters

Connection rules and network-upgrade costs for data centres of 50MW or more will be set separately in each of the six regions, with grid operators’ responses due 17 Aug 2026.

When
18 Jun 2026
ID
WTA-N-2026-0059
Who
FERC, Department of Energy, PJM Interconnection, MISO, SPP, CAISO, ISO New England, NYISO
Rules involved

Summary written with AI by wheresthe.ai, from Vinson & Elkins and the reporting credited above. We could not open the primary document, so it is marked Reported. Checked against the source on 7 Oct 2026.

Source copy: saved on 18 Oct 2026 to check this story and not republished, because the text belongs to its publisher. Also held by the Internet Archive.

Next stop on this Storyline: PromptedEmerald AI, Google and NVIDIA form alliance for grid-flexible AI data centres

Data to measure this

Compare the years before 2026 with the years since in these series.

  • Epoch AI: frontier AI data centresEpoch AISite-level timelines of IT power, compute (H100-equivalents) and capital cost for large AI data centres.live · download · CSV
  • IEA Energy and AI dataInternational Energy AgencyWorld and regional data-centre capacity, power usage effectiveness, load factor and electricity use.download · XLSX
  • TOP500 supercomputer listTOP500.orgThe 500 most powerful computer systems, ranked twice a year, with country, site and hardware.Years: 1993-2026 · semi-annual · query tool · Covers before and after

All data for United States

Cite this story

WTA-N-2026-0059: “FERC orders six US grid operators to fix or defend rules for connecting data centres.” wheresthe.ai, 18 Jun 2026. https://wheresthe.ai/d/us-ferc-large-load-show-cause-orders-2026-06/ (source: Vinson & Elkins).

Spotted an error? Email [email protected].