FERC orders six US grid operators to fix or defend rules for connecting data centres
See how this story connectsAfter the Energy Secretary used a rarely invoked power in October 2025 to ask FERC to consider rules for connecting loads above 20MW, FERC chose six tailored Section 206 show-cause orders to PJM, MISO, SPP, CAISO, ISO-NE and NYISO instead of one national rule, defining a large load as 50MW or more. Each must justify its tariff or propose reforms covering study procedures, network-upgrade cost recovery, co-location, flexible-load service and generation adequacy, with responses due 17 Aug 2026.
Why it matters
Connection rules and network-upgrade costs for data centres of 50MW or more will be set separately in each of the six regions, with grid operators’ responses due 17 Aug 2026.
- When
- 18 Jun 2026
- ID
WTA-N-2026-0059- Where
- United States
- Who
- FERC, Department of Energy, PJM Interconnection, MISO, SPP, CAISO, ISO New England, NYISO
- Topics
- Energy and power, Data centres
- Rules involved
- AI Action Plan United States (federal), In force
Summary written with AI by wheresthe.ai, from Vinson & Elkins and the reporting credited above. We could not open the primary document, so it is marked Reported. Checked against the source on 7 Oct 2026.
Source copy: saved on 18 Oct 2026 to check this story and not republished, because the text belongs to its publisher. Also held by the Internet Archive.
Data to measure this
Compare the years before 2026 with the years since in these series.
- Epoch AI: frontier AI data centresEpoch AISite-level timelines of IT power, compute (H100-equivalents) and capital cost for large AI data centres.
- IEA Energy and AI dataInternational Energy AgencyWorld and regional data-centre capacity, power usage effectiveness, load factor and electricity use.
- TOP500 supercomputer listTOP500.orgThe 500 most powerful computer systems, ranked twice a year, with country, site and hardware.
Cite this story
WTA-N-2026-0059: “FERC orders six US grid operators to fix or defend rules for connecting data centres.” wheresthe.ai, 18 Jun 2026. https://wheresthe.ai/d/us-ferc-large-load-show-cause-orders-2026-06/ (source: Vinson & Elkins).
Spotted an error? Email [email protected].