Finland’s permit and supervisory agency, Lupa- ja valvontavirasto (LVV), told Tuike Finland Oy, the company building Google’s planned data centres in Muhos and Kajaani, to stop work that significantly alters the environment at once and by 23 October 2026 at the latest, until the environmental impact assessments for both projects are complete. LVV said large-scale preparatory work had already been done, including tree removal, topsoil stripping, site roads, storage areas and changes to ditches. The order rests on section 32 of the environmental impact assessment act, and LVV said it would consider administrative coercion if the company did not comply.

Why it matters

Google’s Finnish build-out waits on two environmental reviews.

When
6 Oct 2026
ID
WTA-N-2026-0502
Where
Finland
Who
Lupa- ja valvontavirasto, Tuike Finland, Google; Tommi Muilu
Authority
Lupa- ja valvontavirasto (Finland)
Target
Tuike Finland Oy (Google)
Action
order to halt site work until environmental reviews end
Status
in force · Enforcement ledger

Summary written with AI by wheresthe.ai, from Lupa- ja valvontavirasto (release, in Finnish) and the reporting credited above. Checked against the source on 29 Oct 2026.

Source copy: saved on 29 Oct 2026 to check this story and not republished, because the text belongs to its publisher. Also held by the Internet Archive.

Next stop on this Storyline: Led toFinland asks police to investigate work at Google’s Muhos data centre site

Cite this story

WTA-N-2026-0502: “Finland orders a halt to site work at two Google data centres until environmental reviews end.” wheresthe.ai, 6 Oct 2026. https://wheresthe.ai/d/fi-finland-orders-halt-to-work-at-google-data-centre-sites-2026-10/ (source: Lupa- ja valvontavirasto (release, in Finnish)).